S&E registration, factory licence.

Not yet verified against an official source

Punjab Shops and Commercial Establishments Act, 1958

Registration
The employer sends the prescribed statement within thirty days of the establishment starting work, and is issued a registration certificateSection 13(1) and (3)
Renewal
By 31 March each year, with thirty days of graceSection 13(2)(ii)
Fee
None. The Labour Department states that no fee is chargeable to register a shop or commercial establishmentLabour Department, Shop & Commercial service page, read 19 September 2026
How long it takes
The department's service standard is a certificate within 24 hours of a complete applicationLabour Department, Shop & Commercial service page, read 19 September 2026
Changes and closure
A change in the registered particulars is notified within seven days; closing the establishment is notified within ten days and the certificate cancelledSection 13(4) and (5)